Date:8 Sep.

Last update: 25Aug. 2006

Old Abandoned Project Title:
Proposed Industrial Estate Development on Lot 2968, 028929, 028930, 028931 and part of Lot 2629 (80 acres), Mukim Petaling for Korakyat Plantation Sdn. Bhd.
(Construction Cost: RM 70 Millions)
Project Restarted in 2003 As:
The Rehabilitation Project of Cadangan Pembangunan Perindustrian At Lot-Lot 2968, 028929, 028930, 028931 Dan Sebahahagian Lot 2629(P.T. 24900, P.T. 24901) Mukim Petaling, Daerah Petaling, Selangor Darul Ehsan
(Construction Cost: RM 29 Millions)

I_Proj0120_200x133_02.gif (10435 bytes)

Half Completed 1½ Storey Terrace Unit
Prior To Recommencement

I_Proj0120_200x130_05.GIF (14684 bytes)

Formation of Earth River Bund Along
The Existing Klang River

I_Proj0120_200x135_06.GIF (15774 bytes)

Completed 1 ½ Storey Semi-Detached
Factory With CF

I_Proj0120_200x135_06.GIF (15774 bytes)

Flood Gate At One of the Discharge Outfalls


This project consists of the construction of a total 474 no. Industrial factory buildings of Single Storey Terrace, 1½ Storey Terrace, Double Storey Terrace and 1½ Semi-Detached together with car park, surau, substation, Gerai and other infra-structure.

The site occupies an area of 80 acres running along Klang River for 2km length. It is narrow and long with a drain reserve of 50 feet width.

An economical earthwork platform level has been carefully designed following the detailed study of the surrounding drainage scheme, Master Plan of Klang River Flood Mitigation and careful consultation with the authority.

Developer:

Korakyat Plantations Sdn. Bhd. (In Liquidation)
c/o Ler Lum & Co.

Project Manager

: Seriseti Sdn. Bhd.

Architect : Arkitek C.T.S.
C & S Engineer : SY Perunding
M & E Engineer : G.S. Yang Consulting
Quantity Surveyor : PCM Kos Perunding

Turnkey Contractor (before project abandoned):

Amcorp Builders/Bennes Engineering Sdn. Bhd.

New Main Contractor (after project resume back) :

Bina Goodyear Bhd.


The platform levels also facilitate internal drainage and sewerage flow using gravity system, approved by authority. Due to unforseen factors, the rainwater was modified to flow through outfall structures before discharging into Klang River. Floodgates were designed & installed at the discharge point to prevent back flow of river water.

The sewerage is treated by Extended Aeration Treatment Plant to class A. The external water supply is tapped from existing PUAS’s main pipe and distributed by gravity to each unit.

The buildings are of reinforced concrete column, beam and slab system on reinforced concrete piles.

The development has initially undertaken by developer Korakyat Plantations Sdn. Bhd in 1995. However, it was abandoned in 1998 during the currency crisis.

The old developer has since being in liquidation. The liquidator, Ler Lum & Co in 2001 has implemented a self-help rehabilitation scheme known as Scheme of Arrangement under the provisions of Section 176 of the Companies Act 1965, implemented under the sanction of Court.

The development has recommenced in 15th December 2003. There are a lot of site and technical complications for this recommenced project, which has been abandoned for several years with presence of squatters. There were problems of status of work, structural rectification, complication of new Authority requirements, joining with new neighbouring development.

The Certificate of Fitness for the whole project is obtained on 13th July 2005.


Ad-here
Contry Height Holding Berhad

SY Perunding Sdn. Bhd. All Rights Reserved. [Privacy policy]  [Term of use]

Address: 16, Jalan SS3/31, 47300 PETALING JAYA, Selangor, Malaysia. Email: syp@po.jaring.my

If encounter any problem viewing this page or there is any comment, please email to us at syp@po.jaring.my

or call us at 603-78774470 during office hour